Re: If I read right...
The revenue is a big thing, something that i have to say Wise County had needed for a long time.
But the early spin off will help alot, not just Wise County. Plus the addition of more mining jobs. To me this is a plus for all of the region.
For Wise County it is a big deal, due to the long lasting effect of long term and high paying jobs, and the revenue from the project.
-
Re: If I read right...
Something that surprised me a little on news a minute ago was that they said it would not be producing any power until 2012. Thats a little surprising. I read that it would take 3 years just to construct the place.
-
Re: If I read right...
this will be good. [img]/LDPforum/ubbthreads/images/graemlins/getsmile.tmp007816300.gif[/img]
-
Re: If I read right...
I think bub the reason it's not scheduled to go online till 2012. Construction won't start for a 1 1/2 yrs from the time of annoucement.
A lot of paper work and other planning. This is just the first step in the process.
Didn't understand it myself at first.
But after looking at the scope of what all is required to install a power plant. It will take that long to get up and started.
I think the plant at Carbo took almost 3 years, if not longer. And they are continually working there. Have to meet a lot of ever changing requirements.
There is a lot of permits required, and a lot of request to be done.
And pre-construction work done before the real construction will begin.
So your looking at not starting, full construction, till almost 2008, and 3 yrs for construction, and almost a year for startup, which will put you almost to 2012.
-
Re: If I read right...
I said preliminary because there is environmental studies and all that junk that have to be done first. This type of project takes a wee bit of time.